Municipality:
Podujev
Project type:
School
Investment value:
€303,965.01
Year:
01/05/2023
Area:
3,500.00
Status:
Përfunduar
Electricity consumption before implementation of EE measures:
KWh/vit: 620,600.00
MWh/vit: 423.4
Electricity consumption after implementation of EE measures:
KWh/vit: 196,720.00
MWh/vit: 196.72
Electricity savings after implementation of EE measures:
KWh/vit: 423,410.00
MWh/vit: 423.41
Savings percentage:
68%
CO₂ reduction (tons/year):
34.6
Implemented Measures
-
Thermal insulation of external walls
-
Thermal insulation of the roof
-
Replacement of doors and windows
-
Replacement of lighting fixtures with LED ones
-
Automation of the heating system
-
Renovation of the heating/cooling network
-
New pellet boiler